Grid connection and green power
Boundary
- InferenceFrom the public grid or a direct green-power line to the campus high/medium-voltage incoming feeders.
Interfaces and neighbours
- FactUpstream can be the grid company or a renewable project supplying a single user over a direct line; for grid-connected direct-supply projects, safety responsibility is split at the property boundary.[S03 · 条目一、条目十]
- InferenceDownstream connects to N2, medium-voltage distribution and transformation.
Who pays
- FactDirect green-power projects must still pay transmission and distribution charges, system operation charges, policy cross-subsidies and government funds and surcharges.[S03 · 条目十三]
- GapS03 does not mention data centers at all; it is cited only for charges and responsibility boundaries at grid connection, not as a data-center rule.
Revenue and cost
- GapThe share of electricity in data center operating cost, grid-connection approval time, and dual-feed or high-reliability supply charges: no primary source obtained.
Risks and constraints
- FactThe 2024 plan targets green power above 80% by end-2025 for new data centers in national hub nodes (applies only to new projects in hub nodes).[S01 · p3,二(四)]
- FactFor existing data centers below the energy-saving level and those under construction or planned that miss the advanced level, the 2024 plan uses the wording "study" tiered electricity prices based on the efficiency gap.[S01 · p4,三(一)]
- GapThat wording does not establish that tiered pricing has been implemented; its current status has not been verified here.
Verified source-record associations
No verified source-record association yet. This does not mean the stage has no companies, only that none is verified on this site.